Team Members - Project Manager x 1. Engineer x 2.
Users - NA
Project Duration - 3 Months
Project Effort - 10 Person-Months
Sites - Tokyo, Kanagawa
Problems
• Localization required for new OS OS/2.• Must make new release of OS compatible with existing applications.
• Project to be completed quickly
Solution
• Debug and re-code certain portions of code.• Create dev't and test tools. Provide detailed docs to IBM USA to allow further testing and coding there.
• Proceed in organized fashion with good project management practices.
Benefits
• Project completed within timeframe.• IBM America team satisfied with English bug reporting. Good team rapport established.
• Many bugs fixed.
Technology Highlights
• Custom "purpose use" software created for purpose.• Special dev't techniques for OS/2 developed.